Project Construction Timeline

Below is an outline of the key dates of the Goose  Harbour Lake Wind Farm project's construction. This timeline generally represents certain key milestones that can be expected in the coming years. Note, this is subject to change.

2024

1st Quarter

  • Tree clearing completed

2024

2nd - 3rd Quarter

  • Land Surveying
  • Continued Environmental Studies

2024

4th Quarter

  • Limited Civil Works begins

2025

1st - 2nd  Quarter

  • Transmission Line and Switching station
    ‍‍

2025

2nd - 4th Quarter

  • Civil Construction of Roads, Foundations, Substation and O&M Building
    ‍‍‍

2026

2nd - 3rd Quarter

  • Wind Turbine Delivery and Erection
    ‍‍

2026

4th Quarter

  • Commercial Operations Commences